Production timeline

A transparent path from brief to dispatch

We are committed to clear, efficient project coordination. The timeline below is indicative; some stages may overlap, and actual lead times depend on formulation complexity, material and packaging availability, testing requirements, artwork approval and order quantity.

Stage durations at a glance

Each bar spans the minimum to the maximum working days published for that stage. Some stages may overlap in practice, and actual timing depends on formulation complexity, material and packaging availability, testing requirements, artwork approval and order quantity.

Before order confirmation

  1. Initial consultation & concept brief

    ≈ 2 working days

    We review your product objectives, target market, preferred dosage form, ingredients and commercial requirements.

  2. Formula development

    ≈ 5–10 working days

    We develop or refine a formula based on your requirements and technical feasibility.

  3. Feasibility review & quotation

    ≈ 3–5 working days

    We review the project scope, key materials, packaging and estimated costs before issuing a detailed quotation.

  4. Sample development & evaluation

    ≈ 2–4 weeks

    A physical sample is prepared for your evaluation. Additional revisions may require extra time.

  5. Order confirmation

    ≈ 1–2 working days

    Once commercial terms, formula and packaging details are confirmed, the project proceeds to procurement and production planning.

After order confirmation

47–69Working days

  1. Raw material & packaging procurement

    ≈ 4–6 weeks

    Required raw materials and packaging components are sourced and scheduled for delivery.

  2. Incoming quality checks

    ≈ 5–7 working days

    Materials are reviewed and checked according to established procedures before use.

  3. Manufacturing & packaging

    ≈ 3–4 weeks

    The product is manufactured and packed according to approved specifications and the production plan.

  4. Finished product testing & release

    ≈ 5–10 working days

    Finished goods undergo the required quality checks and testing before release.

  5. Dispatch preparation

    ≈ 2 working days

    Released products are prepared and packed for collection or shipment.

These stages run before the project is committed. The typical lead time is measured from order confirmation onward, so time spent here is additional to it.

Typical lead time: 2–3 months

Measured from order confirmation, subject to the final formula, material availability, packaging, testing and project requirements. If you supply approved raw materials, the timeline may be shortened following a suitability review and incoming quality checks.